Desert Gold Provides Update on Barani East Gold Project Site Development Activities

February 11, 2026 5:30 AM EST | Source: Desert Gold Ventures Inc.

Surrey, British Columbia--(Newsfile Corp. - February 11, 2026) - Desert Gold Ventures Inc. (TSXV: DAU) (FSE: QXR2) (OTCQB: DAUGF) (the "Company") is pleased to provide an update regarding ongoing development activities at its fully permitted Barani East gold project in western Mali.

As outlined in prior news releases and supported by the Company's updated Preliminary Economic Assessment ("PEA"), the Company is advancing the Barani East gold project through a staged approach focused on infrastructure readiness, risk reduction and disciplined capital deployment. In line with this approach, the Company has initiated a series of site preparations and infrastructure works that will be completed in parallel with the manufacturing and delivery of a gravity processing plant and equipment.

"These activities reflect our disciplined, phased approach to advancing the Barani East oxide gold project," said Jared Scharf, President and CEO of Desert Gold. "Completing site preparation ahead of plant delivery and installation will reduce execution risk and support efficient advancement of the project as we progress. Our main goal is to advance the development timeline to commercial production as expeditiously as possible."

Site Preparations and Infrastructure Activities

Current and planned activities include civil works and infrastructure development intended to prepare the site for future plant installation and commissioning. These activities include, but are not limited to:

  • Site clearing, earthworks, and cut-and-fill activities

  • Upgrading access roads and construction of internal roads servicing the plant site, ROM pad, waste areas, water infrastructure

  • Preparation of the ROM pad and processing plant platforms

  • Construction of plant foundations and associated structural works

  • Development of water supply infrastructure, including boreholes, pumping systems, and pipelines to water storage facilities

  • Construction of water management structures, including ponds, diversion drains and spillways

  • Installation of drainage and environmental control measures

  • Installation of site utilities, security cameras and fencing and lighting

  • Construction and upgrading of site offices, control room facilities, and camp infrastructure

These works are intended to reduce future construction timelines and support efficient execution of subsequent development phases.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4954/283470_2da86096f44448e6_001.jpg

Figure 1. (A) Final Pit Design for Barani; (B) Proposed Site Layout for Infrastructure (Taken from recent PEA published on Jan. 09, 2026).

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4954/283470_2da86096f44448e6_001full.jpg

Processing Equipment Procurement

The Company has advanced procurement of a modular, gravity-based gold processing plant as part of its phased development strategy. The selection and configuration of the processing equipment align with the conceptual development framework evaluated in the Company's most recently completed PEA (see news release dated November 25, 2025).

The initial processing plant configuration has been designed for a nominal throughput capacity of approximately 10 tonnes per hour, subject to feed characteristics, commissioning performance and operating constraints. The modular design allows for future expansion, with the overall circuit conceptually capable of supporting increased throughput of up to approximately 50 tonnes per hour under a staged development scenario. This is consistent with the concepts designed in the PEA and it is management's intention to pursue this expansion strategy. Such expansion will be subject to further technical evaluation, infrastructure availability and funding.

The processing equipment is currently under manufacture and is expected to be delivered to site following completion of factory acceptance testing and applicable logistics milestones.

Following installation, initial activities will focus on equipment commissioning, operational readiness, and metallurgical validation. As outlined in the PEA, gravity gold recoveries of approximately 68% were achieved during the metallurgical test work conducted as part of the Company's PEA (see PEA filed on SEDAR+ on January 9, 2026).

Material not recovered during gravity processing is planned to be stockpiled on site for potential future processing. The PEA contemplates additional downstream processing, including carbon-in-leach ("CIL"), as part of a longer-term development scenario, subject to the availability of infrastructure and funding. Metallurgical test work referenced in the PEA indicates that CIL processing has the potential to achieve gold recoveries of up to approximately 92% under laboratory conditions, compared to gravity-only processing. However, these results are preliminary in nature and may not be representative of operating-scale performance (see PEA filed on SEDAR+ on January 9, 2026).

Table 1. Conceptual Metallurgical Recovery Assumptions for Barani East.

Processing StageRecoveryBasis
Gravity Recovery~68%PEA Metallurgical test work
Gravity + CIL (Conceptual)~92%PEA Metallurgical test work

 

Development Strategy

Desert Gold believes this phased development approach provides a practical and disciplined pathway for advancing the Barani East gold project while maintaining capital efficiency. This strategy is intended to allow the Company to continue progressing key development activities in a measured manner as technical work advances and funding options are evaluated. The Company expects to provide updates to the market as material milestones are achieved.

On Behalf of the Board,

"Jared Scharf"

___________________________

Jared Scharf
President & CEO

Additional Disclosure - Development and Economic Uncertainty

The Company cautions that the decision to advance site development activities and conduct commissioning and metallurgical testing prior to the definition of Mineral Reserves involves significant technical and economic uncertainty. As outlined in National Instrument 43-101 Companion Policy 43-101CP, mineral projects that have not defined Mineral Reserves are considered to have a higher risk of failure, and there is no assurance that the Project will be demonstrated to be economically viable. Key risks include, but are not limited to, uncertainties related to metallurgical performance, operating costs, gold recoveries, scale-up of processing infrastructure, logistics, and the availability of sufficient financing. There is no certainty that further technical work will result in the declaration of Mineral Reserves or that any future development scenario would be economically viable.

Qualified Person Statement

The scientific and technical information contained in this news release has been reviewed and approved by Ty Magee (M.Sc., P. Geo), a Qualified Person as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects. Mr. Magee is an advisor and consultant to Desert Gold Ventures and is considered independent of the Company.

About Desert Gold

Desert Gold is a gold exploration company which controls properties in both Mali and Cote d'Ivoire. This includes the 440km2 SMSZ Project in western Mali as well as the newly optioned 297km2 Tiegba gold project in western Cote d'Ivoire within the prolific Birimian greenstone belt.

Contact

Jared Scharf, President and CEO
jared.scharf@desertgold.ca
phone: +1 (604) 357-4726
www.desertgold.ca

This news release contains forward-looking statements. These forward-looking statements entail various risks and uncertainties that could cause actual results to differ materially from those reflected in these forward-looking statements. Such statements are based on current expectations, are subject to a number of uncertainties and risks, and actual results may differ materially from those contained in such statements. These uncertainties and risks include, but are not limited to, the strength of the capital markets, the price of gold; operational, funding, liquidity risks, the degree to which Mineral Resource estimates are reflective of actual Mineral Resources, the degree to which factors which would make a mineral deposit commercially viable, and the risks and hazards associated with mining operations. Risks and uncertainties about the Company's business are more fully discussed in the company's disclosure materials filed with the securities regulatory authorities in Canada and available at www.sedarplus.ca and readers are urged to read these materials. The Company assumes no obligation to update any forward-looking statement or to update the reasons why actual results could differ from such statements unless required by law. Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This news release does not constitute an offer to sell or a solicitation of an offer to buy the securities described herein in the United States. The securities described herein have not been and will not be registered under the United States securities act of 1933, as amended, and may not be offered or sold in the United States or to the account or benefit of a U.S. person absent an exemption from the registration requirements of such act.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/283470

info

Source: Desert Gold Ventures Inc.

Ready to Announce with Confidence?

Send us a message and a member of our TMX Newsfile team will contact you to discuss your needs.

Contact Us